Tuesday, September 3, 2013

Update 9/3

Procured/Ordered Parts:

  • Fuel Rails
  • Reluctor Wheel
  • Throttle Body
  • Wiring Harness
  • Fuel Injectors
  • ECM
Team member assignments and Gantt chart for the rest of the semester is up.

Design has started for coil brackets, reluctor wheel mount, and crank sensor mount.

CAD work has been started for procured parts.

For Next Week:
  • Get more parts
  • Continue with design work
  • Continue with CAD work